Intera Group

Who They Are

Address

213 Miller Street, North Sydney

Scope of project

Construct

Program to complete:

4 weeks

Cost of fitout

$195k per level

Timeline

7 Levels of bathrooms

SCOPE OF WORKS

  • Construction 7 new bathrooms consisting of 3 male cubicles, 2 x urinals, 3 x female cubicles
  • Supply and install of new P50 set ceiling throughout
  • Supply and install of new Elle Wood floor tiles, Charcoal tiles and Black Penny Round tile + waterproofing
  • Supply and install of all tapware, fixtures, fittings and hardware for bathrooms
  • Supply and install of new LED strip lighting throughout and Domus Deco 13W downlights throughout
  • Supply and install special joinery vanity and cubicles for male and female bathrooms